Your project
Repairing or rebuilding a defective shared wall
A repair can raise different rights and cost questions from an extension built for one owner’s benefit.
Establish why the work is necessary before deciding the method or who should pay. Shared does not automatically mean a fifty-fifty bill.
Get the defect assessed
Cracks, damp or an out-of-plumb wall need an informed diagnosis. A structural problem, failed weathering and a maintenance issue can require different responses. Collect dated photographs and the relevant professional findings. Discuss whether temporary protection or urgent safety measures are needed rather than assuming that the final rebuilding scheme is the only immediate option.
Distinguish repair from improvement
Section 2(2)(b) concerns making good, repairing, or demolishing and rebuilding a party structure or party fence wall where necessary because of defect or want of repair. Increasing a wall’s capacity solely to suit a new project may involve other provisions. Explain which part of the proposal addresses the defect and which part improves the building for a new use.
Understand how contributions are considered
For qualifying defect-related works, section 11 considers the use made or to be made of the structure and responsibility for the defect. It does not prescribe an automatic equal split. Keep evidence about condition, maintenance history and the proposed scope. Costs attributable to an additional improvement should be distinguished from the necessary repair when discussing the account.
Plan notice and protection
A repair to a party structure will normally need the relevant party structure notice. The Act includes a specific exception relating to compliance with statutory dangerous or neglected structure notices; an owner should not assume every urgent job falls within it. Obtain prompt advice on the correct procedure and safe temporary measures where the condition is serious.
General guidance for England and Wales, rather than a determination of an individual case. Legal points reviewed on 27 October 2026.
Sources: Act section 2, Act section 3, Act section 11; Government explanatory booklet. Government material is available under the Open Government Licence v3.0.