The key point

Record the issue promptly, notify the relevant people and have the cause and remedy assessed. If there is an immediate safety concern, seek urgent help.

Make a clear record

Note when the issue was first noticed, its exact location and what work was happening nearby. Take dated wide and close-up photographs. Keep any earlier condition record and correspondence. Avoid repeatedly decorating over the same area before its cause has been considered. Where urgent work is necessary for safety or to limit damage, retain evidence and records of what was done.

Tell the right people promptly

Notify the building owner and the appointed party wall surveyor or surveyors where there are appointments. Inform your insurer where the policy requires it. A contractor’s informal assurance may not resolve responsibility or the correct repair. Describe the facts and ask what inspection or protective action is needed, rather than making a final diagnosis from the appearance of a crack.

Separate cause from remedy

The Act provides for compensation for relevant loss or damage and, where applicable, making good. A new defect is not automatically proof that the neighbour’s work caused it; equally, prior consent does not remove statutory responsibilities. The surveyors may need the construction sequence, condition record and technical advice to determine the issue and appropriate response.

Agree the repair or payment properly

Section 11(8) provides a route for expenses of making good to be determined and paid in lieu of the work where the statutory conditions apply. Keep the agreed scope, access and finish clear. If there is no valid statutory process or another legal claim is involved, obtain advice on the appropriate route rather than assuming a later Award can retrospectively authorise everything.

General guidance for England and Wales, rather than a determination of an individual case. Legal points reviewed on 27 October 2026.

Sources: Act section 7, Act section 10, Act section 11; Government explanatory booklet. Government material is available under the Open Government Licence v3.0.